Thursday, May 20, 2010

The Latest

Our architectural plans are still being reviewed by Cibolo. Our plat review hasn't officially begun yet. Additionally, we've been looking for an alternative solution to supply our water needs. The talks have only been preliminary at this point. The parking expansion - I really am surprised at the hoops we are having to jump through for pavement. We've had two different reports indicating that we would have already started (if not completed) adding nearly 60 parking spaces. The news we received last week says we are still 2 weeks away from starting. If we aren't dealing with bad weather the parking expansion should take four to five weeks from start to finish.

Join me in praying for these various phases. I'm learning more about commercial construction than I would even want to know. The delays are taking their toll, but I'm beginning to think there are more delays ahead than I can predict. Thank you for your faithful support in our BELIEVE Expansion Project. Keep the faith.